In an opinion issued this week in N-Tek Construction Services, Inc. v. Hartford Fire Insurance Company, the Massachusetts Appeals Court ruled that a sub-subcontractor’s e-mail to a general contractor on a public construction project failed to clearly present a claim that would satisfy the notice requirements of M.G.L. c. 149, s. 29.
The unpaid sub-subcontractor on a public bridge painting project sent an e-mail to the general contractor that stated the following. “Enclosed is the January 15, 2010 Statement to [subcontractor] for services through that date by [sub-subcontractor] for the [project] that are still unpaid. Please give me a call at [telephone number] when you have a chance.” The attached Statement listed ten invoices. The general contractor’s project manager testified to having never heard of this sub-subcontractor prior to the e-mail, and did not understand the e-mail to be some form of claim.
M.G.L. c. 149, s. 29, requires parties that do not have a direct contractual relationship with the general contractor to provide written notice to that general contractor of any claims of non-payment within 65 days of last providing labor or material on the project. The statue merely requires that the notice state “with substantial accuracy the amount claimed, [and] the name of the party for whom such labor was performed.”
The Court’s opinion included a nuanced analysis of the purpose of this notice requirement. It held that the implied purpose is to give general contractors a clear, timely understanding that a claim is being directed against them. This is to allow an opportunity to attempt to resolve the claim prior to litigation and involvement of the payment bond surety.
In ruling against the sub-subcontractor, the Court looked at all of the circumstances surrounding the e-mail and deemed it inadequate, for failing to state “explicitly or implicitly” that the e-mail constituted a claim for an unpaid balance due on the project.
Sub-subcontractors and material suppliers on public construction projects in Massachusetts should consult with a construction attorney prior to sending 65-day notices to general contractors to insure the preservation of their payment bond rights.